PROJECT TIMELINE

Obtain non-profit status                            Completed Feb. 2018

File for Enterprise Zone status                  Approved August 8, 2018 

 

Find land for development                        Purchased 4-30-20

Oct. 29, 2019                       

                                                          

File PUD application with Town                Approved 3-9-20

Fundraising campaign to                           Completed 4-30-20

purchase land & begin

preliminary development

                             

Submit grant applications for                    Summer/Fall 2020

funding of Architect and Engineer 

Project design                                             Fall/Winter 2020

                                                                          

Submit LWV design plan to Town for       Winter 2020

final PUD approval

 

Submit grant applications                         Spring 2021

for construction

                             

Begin construction                                     Fall 2021

                             

Ready for occupation                                Winter 2021 – Spring 2022           

 

                                                 

Crestone Peak Community Housing

PO Box 911
Crestone, CO 81131

CrestonepeakCH@gmail.com

Hours 10am to 6pm MST 

719 937 7784 or 719 256 4320

© 2018 by Crestone Peak Community Housing Web site created by Lori Nagel.